Endeavour Silver ($EDR)’s 19 November feasibility study for Pitarrilla puts after-tax net present value at US$736m, discounted at 5%, using US$50/oz silver. In its published US$30/oz sensitivity, NPV falls to US$109m and the internal rate of return falls from 16.37% to 7.00%. Original release, pages 1–5.
Both cases retain positive modelled value. They offer quite different compensation for committing capital to a new underground mine. We would begin the development discussion with that sensitivity, rather than treating the headline NPV as an amount shareholders can collect.
The distinction matters even for a company willing to take a long view on silver. A development decision commits money before the commodity-price outcome is known. The useful question is whether the project can tolerate a less helpful outcome while the company meets its other obligations.
The lower-price case gives the headline some context
The Mexican project’s US$585m initial capital estimate includes US$65m contingency; another US$119m of sustaining capital is modelled over its life. Endeavour expects to fund most construction from existing cash and future cash flows from operating mines. Additional approvals and amendments remain outstanding, including the tailings-storage permit. Pages 2 and 4.
That funding approach could reduce reliance on a large new equity issue. It also connects the proposed build to the performance and spending requirements of existing operations. Expected cash generation can support a plan without becoming an irrevocable financing commitment.
For a financing decision, we would want to see the timing of construction payments alongside conservative operating cash forecasts, debt service and other capital commitments. The total initial estimate alone cannot reveal the deepest funding requirement or the cash reserve management should retain.
The cost work deserves the same attention. A contingency allowance can absorb some uncertainty, but it cannot promise that every design change, approval condition or construction delay has already been priced. A sensible funding plan should leave room for the study to be refined.
Follow payable silver through the calculation
The study models approximately 5.4Moz of physical silver annually, alongside lead and zinc. Its silver-equivalent measure combines metals using stated ratios. Across the mine life, 97.78Moz silver produced becomes 88.67Moz payable. Its US$15.06/oz mine-site AISC uses payable silver and by-product credits. Pages 2–4.
Investors should keep those conventions together. Multiplying gross silver output by a price and subtracting a payable-ounce cost would mix denominators. By-product credits also depend on the other metals’ economics; they are part of the business rather than a permanent deduction from its risks.
The constructive evidence is meaningful. Endeavour has a defined underground development concept, a feasibility-level assessment and a published lower-price case that remains positive. That gives potential financiers a concrete plan to examine.
The next decision still requires judgement about timing, financing and execution. We would compare funding capacity with several price cases before relying on the base-case return. Pitarrilla could become an important operating asset, but the investment case needs to survive the period when the company is paying for construction and receiving no production from it.