Forrestania Resources ($FRS) has signed a long-term sodium cyanide supply agreement with Australian Gold Reagents for Edna May and awarded Campbell Gold Haulage its ore-loading and crusher-feed contract. The 20 November release describes equipment and personnel mobilisation under way. Original filing, page 1.
These are useful details because a gold restart depends on more than having a plant and a stockpile. Operators need to move ore through the circuit, supply the necessary chemicals and keep each part working together. A missing service can interrupt production even when the main equipment is ready.
We would give more weight to an executed reagent agreement than another general statement about readiness. It addresses a specific requirement. It still needs to translate into deliveries and effective operation as commissioning proceeds.
Two stockpiles serve two hubs
Management reports approximately 60,000 tonnes of ore on the Edna May run-of-mine pad and more than 180,000 tonnes of inventory at Lake Johnston. These are separate locations. The release identifies the contracts as components of the move from dry to wet commissioning. Page 2.
A run-of-mine pad holds material before processing. Its tonnage can support continuity of feed, but it cannot establish recoverable gold without the relevant grade, blending and recovery information. Combining the two stockpiles into a single assumed Edna May feed balance would also obscure which operation can use the material.
Campbells already holds the road-train contract, and Forrestania expects efficiencies from integrating that work with loading and crusher feed. Those interfaces matter: haulage performance has limited value if ore cannot be unloaded or fed when required. The announcement does not quantify a realised cost saving. Pages 1–2.
The next operating report can show whether the arrangements support consistent feed. We would look for tonnes processed, grade and recovery on clearly stated periods, rather than infer an annual rate from a brief commissioning run.
December remains a target
Forrestania says dry commissioning is well under way and targets first gold in December 2026. It has also established a Kalgoorlie operational office shared with MEGA Resources. Pages 1 and 4.
First pour would demonstrate that the restart has progressed through another important stage. It would leave further questions about sustained availability, output and the costs of operation. A first bar and a profitable steady operating month answer different questions, and both deserve to be reported when they occur.
The constructive case is straightforward. Forrestania has ore available and is arranging the services needed to process it, rather than relying solely on exploration potential. Coordinating road haulage and pad handling may also reduce avoidable disruption. Those are credible reasons to follow commissioning closely.
We would change the emphasis from readiness to economics once the company can show repeatable throughput and recovery, followed by sales and a reconciled cash result. Until then, the reagent and handling contracts are practical advances towards the proposed pour. They do not establish completed wet commissioning or cash generation.
Follow-up — 25 November 2026
Forrestania and Javelin have announced a new conditional ore purchase agreement. The new review explains its volume ceiling, takeover conditions, delivery tests and gold-price termination provisions. The commissioning facts and dates above remain those originally reported on 20 November.