Koryx Copper ($KRY)’s 17 November Haib pre-feasibility results put a specific processing decision behind the headline economics: crush 48 million tonnes a year of run-of-mine material, reject approximately 25% of that mass through coarse particle flotation, and send the remaining 36Mtpa to conventional flotation. The rejected gangue is unwanted material separated from the copper-bearing feed. Original release, pages 3–4.
That step matters at a deposit whose modelled mining head grade averages 0.32% copper in the first ten years and 0.27% over the operating life. The corresponding flotation-feed grades are 0.42% and 0.35%. Removing mass before the final concentration stage can reduce the material that must be treated there, provided copper losses remain acceptable. It does not mean discarding a quarter of the copper. Table 3.
A simpler flowsheet still needs operating proof
The company says the new plan abandons the earlier heap-leach facility. It proposes crushing, milling and flotation, with a life-of-mine copper recovery of 87.3%, compared with 89.5% during the first decade. Those are study forecasts, not an operating plant’s demonstrated performance. Pages 1–2.
Koryx also identifies the limitation itself. Coarse particle flotation in this application adds operational complexity, while test accountability and tailings-assay differences create uncertainty around copper and molybdenum recovery, especially at lower feed grades. Further pilot work and dynamic simulations remain part of the definitive study. The gold-recovery model is preliminary. Pages 24–25.
The distinction between production measures deserves equal care. Table 3 forecasts 135,000 tonnes a year of copper in concentrate in the first ten years, versus 130,000 tonnes payable. The whole-life payable average is 105,000 tonnes a year. Copper equivalents also include other metals and should not replace physical copper in a supply calculation. Table 3.
Mining is scheduled for approximately 15 years after pre-stripping, followed by stockpile treatment within the 24-year processing life. The lower whole-life average therefore describes a different operating mix, rather than a forecast of an immediate production miss. Page 3.
Water and capital remain part of the process
The US$2.059 billion upfront capital estimate includes US$133 million contingency and US$152 million capitalised pre-strip. A separate US$639 million sustaining-capital estimate covers later spending. These are study costs, not completed financing or a current equity valuation. Table 4.
The base case’s approximately US$2.54 billion post-tax NPV at 8% uses US$5/lb copper, alongside gold and molybdenum assumptions. Its modelled return is conditional on those inputs. The project still requires a definitive study, financing and a construction decision. Pages 1, 3 and 25.
Water is a practical constraint alongside metallurgy. Koryx has applied for 20 million cubic metres a year from the Orange River. Its study warns that growing tailings storage brings evaporation and entrainment losses that can weaken water recovery. Applications and management’s mid-2027 permitting target do not establish granted water rights or resolved community concerns. Pages 24–25.
Haib has a declared Probable Reserve, a specified process and opportunities for further optimisation. We would give the next pilot results and infrastructure approvals at least as much attention as the headline NPV. They determine whether the planned tonnes can be produced at the planned cost.