Minerals 260 ($MI6) has received a works approval for Bullabulling, a day after announcing A$410 million of credit-approved debt commitments. Together, the 11 and 12 November filings give the proposed Western Australian gold operation more concrete support. They also identify exactly what still needs to happen before the banks advance money and the company takes its final investment decision. Bank commitments; works approval.
The debt package comprises a A$335 million project finance facility and a A$75 million working-capital facility from ANZ, NAB and Societe Generale. The company has signed a binding, credit-approved commitment letter and term sheet. That is more advanced than an expression of interest. It is not a report that A$410 million has arrived in the bank. 11 November release, pages 1–2.
Financial close and first draw have different dates
Financial close is expected in the first quarter of calendar 2027, with the first draw expected at the end of 2027. The conditions include long-form documentation, completion of the definitive feasibility study, final due diligence, an intercreditor deed with Franco-Nevada and other customary requirements. The commitments were based on the pre-feasibility study. Page 2.
Minerals 260 says the combination of these facilities, Franco-Nevada royalty funding and the recent equity raising fully funds Bullabulling to first production. That is management's funding conclusion. Readers should assess it against the final study, the conditions and timing of each funding component, rather than treating all three as unrestricted cash available today. Page 1.
The project facility is a seven-year amortising loan with a bullet repayment at maturity; the working-capital facility has a four-year term. Disclosed interest is BBSY plus a fixed margin below 3%, with interest capitalised during construction. Capitalising interest changes when and how it is paid or recorded; it does not make the borrowing free. Page 2.
The terms impose no mandatory gold, foreign-exchange or diesel-price hedging. That preserves exposure to favourable prices and avoids a compulsory hedge requirement. It also leaves adverse price and currency movements relevant to the project's eventual cash generation. No undisclosed covenant or exact margin should be invented to fill out the financing model. Page 2.
The works approval covers important facilities, with conditions
The 12 November notice says the Department of Water and Environmental Regulation has granted the works approval covering facilities including the processing plant, power infrastructure and tailings storage facility. Development remains subject to the Native Vegetation Clearance Permit and Mine Development and Closure Proposal. The company's diagram distinguishes these from earlier approvals for the accommodation village. Page 1.
The remaining approvals are under assessment. Management targets FID in Q1 2027 and first production in 2028. Those are prospective milestones, not completed approvals or a guaranteed first sale. This review relies on the issuer's announcement and does not independently reproduce the regulator's full approval conditions. Pages 1 and 3.
Bullabulling's 6.2 million ounces comes from the resource effective 8 July 2026: 190 million tonnes at 1.0g/t gold, above 0.35g/t within an A$5,250/oz pit shell. The resource includes the project's maiden Ore Reserves; the entire resource is not thereby a reserve or a production schedule. Resource table and notes, page 2.
The constructive argument is substantial: the company has advanced both financing and permitting ahead of the planned decision. We would now watch completion of the named conditions and the final cost-and-schedule assessment. On the disclosed timetable, the next financial milestone is close, followed later by access to the bank funds.
Update — 26 November 2026
Minerals 260 has selected NRW and authorised early mining services, with the long-form contract expected after FID. Read the 26 November contractor and timetable follow-up. The original funding analysis above retains its source dates.