Tungsten Mining ($TGN)’s new Watershed feasibility study reports A$206.6 million of go-forward construction capital. Its funding section puts the remaining funding requirement at approximately A$255 million. Both appear in the 16 November original filing, and they answer different questions. DFS, pages 5 and 10.
The distinction is useful for a project targeting June 2027 first concentrate. A construction estimate explains what remains to be built. A funding plan also has to carry the business through the period before operations generate cash. A large net present value cannot pay a contractor’s invoice on its own.
The funding section includes more than construction
Total pre-production capital is A$264.4 million, including contingency. The disclosed A$57.8 million pre-commitment comprises approximately A$22.4 million spent and A$35.3 million committed, with rounding. An order placed is not the same as money already paid. Page 5.
The unlevered peak funding estimate is about A$277 million, including sustaining and leasing capital and net pre-production operating cash outflows. After roughly A$22 million invoiced to date, the filing gives the approximately A$255 million remaining requirement. These figures are real 2026 Australian dollars and exclude financing costs. They should not be turned into an exact new-equity cheque by subtracting an old cash balance. Page 10.
Tungsten Mining is targeting up to approximately 70% senior debt and reports non-binding term sheets. Financial close and a final investment decision are targeted for December 2026. No binding offtake agreements have been executed, according to the study. Lender due diligence, final funding and customer contracts still have work to do. Pages 9–10.
APT prices are an input to concentrate economics
The base case reports A$1.569 billion pre-tax NPV at 8% and A$1.105 billion post-tax NPV at 8%, valued from November 2026. These are model outputs, not the current value of the listed equity. The base case uses a US$1,500 per metric-tonne-unit life-of-mine average ammonium paratungstate price. APT is a processed tungsten product; the mine plans to sell concentrate on a price and payability structure. Pages 5 and 8.
The forecast therefore depends on more than keeping the quoted APT price high. Buyers must accept the concentrate, its specifications and the commercial deductions. The study uses a price and payability forecast, with an 82% payability assumption beyond 2035; it has not disclosed that as a signed universal sales term. Pages 8–9.
Resource confidence matters too. Around 10% of scheduled mill feed is Inferred. The study separately reports an Ore Reserve-only pre-tax NPV of A$1.4 billion, compared with the A$1.569 billion base case. That is a useful counterargument to assuming the entire economic case rests on the least certain material, while preserving the lower confidence attached to Inferred resources. Pages 18–19.
Principal approvals and early works support the development case. The next test is whether binding financing and offtake preserve enough of those modelled economics to deliver the proposed schedule. That is a better milestone than treating the largest NPV on the page as money already earned.